ETI (ECCO Tannery Indonesia) Project

PT. Lintech Duta Pratama as a partner of ENSYSTA PIPING SYSTEMS ENGINEERING (SHANGHAI) CO., LTD., supply site installation and supervisor related to the Project.

Project Scope:
a. All site installation work for the project
b. Management of local team
c. Site office including office room for Ensysta team (5 persons) and meeting room
d. Workshop and material storage
e. All tools, lifting device and scaffold, temporary power supplier connection for installation
f. Consumables material for mechanical installation
g. Site organization, included travel costs, accommodation costs, people transportation costs
h. Site safety according to the existing safety regulations. 

During expansion ETI (Ecco Tannery Indonesia) project PT Lintech Duta Pratama Under ENSYSTA PIPING SYSTEMS ENGINEERING (SHANGHAI) CO., LTD delivered project with tight schedule and best quality for:

1. Renewal of all utilities such as compressed air, Hot Water system, Cold Water System, City Water, High Pressure System(170 bar), Hot Water Boiler, ST Boiler system,LPG/CNG
2. Process system equipment such as: Dry tunnels, Chemical tank farm, Fencing and Table, Aqua mixing, and Huni systems station, Electrical, also Exhaust and Dust extraction system. 

As Engineering, procurement and construction PT Lintech Duta Pratama also supply 4 Tank for:

  • Storage tank
  • Hot Process Water
  • Fuel Storage Tank
  • Buffer Tank
For System process PT Lintech Duta Pratama also install piping system based on Process and Instrumentation Diagram (P&ID), piping layout, and Isometric Drawing with project rules such as:
  • Installation site safety supervision
  • The off loading
  • The piping and equipment erection
  • The cabinet, cable and cable tray erection
  • Pressure tests, cleaning
  • The support (only workers) of I/O testing, loop check
  • The support (only workers) of Programming and commissionin

 