Lintech operates Ball Front Hydraulic and Flanging Machine (Pressure Vessel End Caps Machine)
- March 2009 -

To catch the vessel market, Lintech has Invested in 8m diameter max ball front press machine with max thickness 75mm in a set wih flanging machine. With this equipment Lintech capable to do ourself the complete fabrication of any shape (bullet, Dished End, etc) of LPG Tank, CO2, Nitrogen and other pressure vessel in compliance with ASME U STAMP & NFPA.

Please contact our sales (marketing@lintech.co.id) for inquiries.

----------------------------------------------------------------------------------------------------------------------

DUPONT-PIONEER PROJECT (Earth Work, civil, steel fab/erection, electrical/instrument,commissioning) has reached 70% progress to date, Safely.
- February 2009 -

It is 2000 ton of steel, up to 4000m3 of concrete, 400 tons of rebar and 20,000 m3 or earth works, bin/conveyors, Electrical power and control system to complete on July 2009.

----------------------------------------------------------------------------------------------------------------------

SWISS PUMP MANIFOLD HEADER REPLACEMENT PROJECT
- January 2009 -

----------------------------------------------------------------------------------------------------------------------

CELEBRATING 10 YEARS of HIGH QUALITY AND COMMITMENT
- November 2008 -

In this moment, 10 years after Lintech established in year 1998, Management Lintech would like to express our appreciation to all our bussiness companion, specially to our customers who have trusted Lintech for the first 10 years. We wish, we will be partners (in Drafting/Engineering, Fabrication & Construction) for next 10 years.

WISHING THE BEST FOR ALL OF YOU IN 2009 and BEYOND.

----------------------------------------------------------------------------------------------------------------------

BLUESCOPE INDONESIA TO TRIPLE CAPACITY OF CILEGON STEEL PLANT
- October 2008 -

There are hundreds to thousand tons of steel involving in this project. Lintech is involving in detailing, fabricate and supply for the steel structures and equipment through many OEM supplying equipments to Bluescope plant. Mostly of design made by european company. We bring steels at ASTM36/JIS/Europe and some Australian Standards AS3678 to our Shop from Arcellor mittal, Krakatau, Onesteel Australia, etc to complete this project.

A solid Lintech engineering and material supply to solve many standards in one project. Fabrication, welding, painting and delivery to be brought to highest quality on the assigned standard.

----------------------------------------------------------------------------------------------------------------------

Lintech Having A Handshake to start DUPONT Corn & Rice Seed Expansion Plant at Malang East Java
- September 2008 -


   

On 4rd September 2008, Lintech has been in conference call for final pricing on the Dupont expansion plant at Malang. The conference was ended in satisfaction manner to both parties.

After Bayer Plant, this is another complete plant that handed over to Lintech to build for Industrial Plant containing integrated Earth Works, Civil foundation, steel structure and mechancial equipment fabrication, erection, electrical power and control system and commissioning.

The standard brought by Dupont is American standard and brands, which is another high quality standard project requirement to be completed by Lintech after Australian, JIS and European standards.

----------------------------------------------------------------------------------------------------------------------

Lintech is starting Export Fabricated Steel to Yarrabee Coal Mine - Brisbane-East Australia
- August 2008 -

The material used for this project is SS355JR (arcellor mittal steel) that equivalent to AS 3678- 350 Mpa, carbon steel high grade. On quality, Lintech is developing a sister company system with AJ MAYR Australia to ensure our Australia Customer receive Australia's high quality final product. On Shipment issue, there are big vessel liner operates regularly to west and east Australia for every two weeks.

----------------------------------------------------------------------------------------------------------------------

BOC Gases - Civil Steel Fabrication and Construction
- May 2008 -

Project Title: BOC Gases - Civil Steel Fabrication and Construction
Design/Manufacturer: PT. LINTECH DUTA PRATAMA

----------------------------------------------------------------------------------------------------------------------

Kutai Shiploader Boogies
- May 2008 -

Project Title: Kutai Shiploader Boogies
Design/Manufacturer: PT. LINTECH DUTA PRATAMA
Project Owner : PEC Tech
Project Customer : Tenova SEMF - Italy
Project Started: January 2008
Project Completion Date: May 2008.

----------------------------------------------------------------------------------------------------------------------

30 Ton Container Overhead Spreader Crane
- February 2008 -

Project Title: 30 Ton Container Overhead Spreader Crane
Design/Manufacturer: PT. LINTECH DUTA PRATAMA
Hoist Brand: Konecranes Double Hoist
Project Started: November 2007
Project Completion Date: APRIL 2008.

----------------------------------------------------------------------------------------------------------------------

Mechanism Assembly of Hidden Valley Project
- 23 January 2008 -

----------------------------------------------------------------------------------------------------------------------

Gresik BOC GASES- Plant Building & Cranes
- 1 December 2007 -

Project Title: Civil, Fabrication & Construction of Process Plant Building, OH Cranes
Project Owner: BOC GASES - GRESIK
Project Customer: BOC GASES
Manufacturer: PT.Lintech Duta Pratama.
Fabrication Site:  NEW LSF-LINTECH SEASIDE FACILITY
Project Started: 1 DEC 2007
Project Completion Date: 29 APRIL 2008.

----------------------------------------------------------------------------------------------------------------------

HIDDEN VALLEY MINING - FLOATATION CELL
- 18 October 2007 -

Project Title:  FABRICATION & ASSEMBLY OF 6 EA-130M3 FLOATATION CELLS
Project Owner:  HIDDEN VALLEY MINING
Project Customer:  FLSMITDH
Manufacturer: PT.Lintech Duta Pratama.
Fabrication Site:  NEW LSF-LINTECH SEASIDE FACILITY
Project Started:  Mid 2007.
Project Completion Date:  30 November 2007.
Delivery Point:  PORT MORESBY - PAPUA NEW GUINEA via SURABAYA PORT

----------------------------------------------------------------------------------------------------------------------

FREEPORT INDONESIA - CONCENTRATE STORAGE TANK
- 18 October 2007 -

Project Title:  FABRICATION & SHIP COMPLETE UNIT 2EA -7M DIA X11M H RUBBER LINED TANKS
Project Owner:  PT. FREEPORT INDONESIA.
Project Customer:  PT. FREEPORT INDONESIA .
Manufacturer: PT.Lintech Duta Pratama.
Fabrication Site:  NEW LSF-LINTECH SEASIDE FACILITY
Project Started:  Mid 2007.
Project Completion Date:  30 November 2007.
Delivery Point:  AMAMAPARE - PAPUA via SURABAYA PORT

----------------------------------------------------------------------------------------------------------------------

PT.INCO FABRICATION 750 KL HSD TANK
- 4 April 2007 -

Project Title:  FABRICATION & SITE ERECTION 750KL HSD Diesel Storage tank
Project Owner:  PT. Inco Soroako.
Project Customer:  PT. Inco Soroako .
Manufacturer: PT.Lintech Duta Pratama.
Project Started:  21 February 2007.
Project Completion Date:  1 may 2007.
Project Construction/Installation:  By Lintech Crew – Start onsite erection Mid April 2007

----------------------------------------------------------------------------------------------------------------------

SWISS PUMP MANIFOLD HEADER REPLACEMENT PROJECT
- 4 April 2007 -

Project Title:  SWISS PUMP MANIFOLD HEADER REPLACEMENT PROJECT
Project Owner:  PT. Newmont Nusa Tenggara.
Project Customer:  PT. Newmont Nusa Tenggara.
Manufacturer: PT.Lintech Duta Pratama.
Project Started:  5 April 2007.
Project Completion Date:  4th July 2007.
Project Construction/Installation: By Lintech Crew - August 2007 Shutdown
Project Detail : 54”-25mm thick Piping with AWWA Flanged – Rubber lined internally for                       Sea Water application

----------------------------------------------------------------------------------------------------------------------

PTFI HPGR PROJECT CHUTE FABRICATION
- 14 February 2007 -

Lintech secured steel structure fabrication for PT.Freeport

Project Title:  PTFI CHUTE FABRICATION, HPGR PROJECT
Project Owner:  PT. Freeport Indonesia.
Project Customer:  PT. Freeport Indonesia.
Manufacturer: PT.Lintech Duta Pratama.
Project Started:  15 January 2007.
Project Completion Date:  8th February 2007.
Steel Tonnage used in the project: 55 tons - ASTMA36

----------------------------------------------------------------------------------------------------------------------

Lintech Seaside Facility (LSF)
- 6 February 2007 -

Lintech start construction of the new facility aggressively.
in order to provide better shipment arrangement and delivery, lintech speed up the construction
progress in the new facility. For shop tour, click this attachment.

Project Title:  Lintech Seaside Facility.
Project Owner:  Lintech Corporation.
Total Investment:  US$ 10,000,000.00
Project Started:  6 June 2006
Project Completion Date:  17 August 2007.
Shop Capacity:  1000 ton/month Heavy Steel Structure.
                        500 Ton/month Tank and Mechanical Steel fabrication
                        2,000 Ton/6 month Offshore Platform/Module

----------------------------------------------------------------------------------------------------------------------

PTFI Pipe Rack Project Fact
- 2 Oktober 2006 -

Lintech secured steel structure fabrication for PT.Freeport

Project Title:  PT.Freeport Pipe Rack.
Project Owner:  PT. Freeport Indonesia.
Project’s Customer:  PT.Freeport Indonesia.
Contract Value:  -
Manufacturer:  PT.Lintech Duta Pratama.
Project Started:  1 November 2006 – 15 January 2007.
Project Completion Date:  8th January 2006.
Steel Tonnage used in the project:  120 tons – ASTMA36.

----------------------------------------------------------------------------------------------------------------------

INCO ESP Project Fact
- 12 September 2006 -

Lintech completing most steel works for PT. INCO.

Project Title:  INCO ESP Project.
Project Owner:  PT. INCO.
Project’s Customer:  BECA-AMEC-INCO.
Contract Value:  USD 2,000,000,-
Manufacturer:  PT.Lintech Duta Pratama.
Project Started:  17th January 2006.
Project Completion Date:  8th January 2007.
Steel Tonnage used in the project:  2,000 tons – ASTMA36.

 

----------------------------------------------------------------------------------------------------------------------

DAIRI Project Fact
- 05 September 2006 -

Lintech receive new order for manufacturing of DAIRI flotation cells.

Project Title:  Dairi’s Lead/Zinc Flotation Cells Project.
Project Owner:  Dairi Mining – Medan-Indonesia.
Project’s Customer:  GL&V Australia.
Contract Value: -
Manufacturer:  PT. Lintech Duta Pratama.
Project Started:  5 September 2006.
Project Completion Target:  12 January 2007.
Steel Tonnage used in the project:  260 tons – ASTMA36.
Rubber Lining used in the project:  Lintech 802 Duro 60 natural wear abrasion resistance
                                                   rubber
.
M2 rubber lining:  6mm thickness x 3,500 m2 area, hot curing system.

Today’s (12 September 2006) progress, 7 days after receiving order.


Copyright © 2006.  PT. Lintech Duta Pratama.                                                                              contact us  |  career  |  site map