Pertamina PPGS Project Package
I
Construction and erection of Condensate Storage Tanks (1,000,000
Lt).
From November 2005 to February 2006.
1. Unloading Equipment 2.
Site Preparation
3. Base Site Inspection
    
4. Bottom Plate and 1st Shell
Erection
5. Outer Side 1st Shell
6. 2nd Shell Erection
    
7. Preparation for 3rd Shell
Instalation
8. 3rd Shell Instalation
9. Welding Guide Stiffeners
    
10. Outer Side Welding
11. Welding inspection (1)
12.
Welding inspection (2)
    
13. Crown, Rafter and Subrafter
14. Nozzles, flanges and gtarings
14. Nozzles, flanges and gtarings
Tank MBT 120 A/B/C
for MBT 120 A/B/C (1)
for MBT 120 A/B/C (2)
    
15. Crown Erection
16. Roof Plates
Installation 17.
Tank MBT 120 A/B/C Finishing
    
|